Dubai’s biggest future road projects: Latest RTA updates, completion status and benefits

New bridges, tunnels and highways: How Dubai plans to beat traffic and cut commute times

Last updated:
5 MIN READ
From Hessa Street and Al Qudra Road to Dubai Islands and the World Trade Centre Roundabout, the developments are designed to increase road capacity, improve connectivity and significantly reduce travel times.
From Hessa Street and Al Qudra Road to Dubai Islands and the World Trade Centre Roundabout, the developments are designed to increase road capacity, improve connectivity and significantly reduce travel times.
RTA/Supplied

Dubai: Dubai continues to invest heavily in road infrastructure, with the Roads and Transport Authority (RTA) rolling out major projects aimed at reducing congestion, cutting travel times and improving connectivity across the emirate.

Several projects are already partially open, while others are nearing completion and set to transform daily commutes for hundreds of thousands of residents.

Here are the key Dubai road projects to watch and how they will impact motorists in the coming years.

Get updated faster and for FREE: Download the Gulf News app now - simply click here.

1. Hessa Street Development Project (Phase 2)

Following the completion of the first phase between Sheikh Zayed Road and Al Khail Road, RTA has begun Phase 2 of the Hessa Street Development Project.

The new phase covers a 3km stretch from Al Khail Road to Sheikh Mohammed bin Zayed Road and includes:

  • 8.8km of bridges

  • A 480-metre tunnel

  • Upgrades to three major intersections

  • Improved entry and exit points on surrounding roads

Key benefits:

Once complete, the project will double road capacity and reduce travel times from 24 minutes to just five minutes. It will also provide a direct connection between Al Khail Road and Sheikh Mohammed bin Zayed Road.

The project is expected to benefit around 650,000 residents across 10 communities, including Jumeirah Village Circle (JVC) and Al Barsha South.

Hessa Street Development Project,

2. Dubai Harbour Direct Access Bridge

RTA has completed around 90 per cent of a major bridge project that will provide direct access from Sheikh Zayed Road to Dubai Harbour.

Opened on June 19, the bridge features two lanes in each direction and can accommodate up to 6,000 vehicles per hour.

The bridge provides direct access to Dubai Harbour from Sheikh Zayed Road, improving connectivity for motorists travelling from Jebel Ali and Deira. According to the RTA, the project cuts travel time in the area from 12 minutes to just three minutes, helping ease congestion and improve traffic flow.

Key benefit - The project will significantly improve access to Dubai Harbour while reducing traffic pressure on surrounding roads.

The Dubai Harbour bridge spans 1,500 metres and comprises two lanes in each direction, with a total capacity of approximately 6,000 vehicles per hour.

3. Oud Maitha Road and Al Asayel Street upgrade

Part of the wider Sheikh Rashid Corridor Development Project, this scheme focuses on improving traffic flow and connectivity across central Dubai.

The project includes:

  • Development of four major intersections

  • A new left-turn slip road from Oud Maitha Road to Sheikh Rashid Road towards Al Garhoud Bridge

  • 4.3km of bridges

  • 14km of upgraded roads

Key benefits

  • Improved connectivity between Al Asayel Street and Al Khail Road

  • 50 per cent increase in Oud Maitha Road capacity

  • Enhanced traffic movement at key intersections

4. Umm Suqeim Street Improvement Project

RTA says approximately 70 per cent of the project has been completed along the 4.6km section between Al Khail Road and Sheikh Mohammed bin Zayed Road.

The upgrade forms part of the larger 16km Umm Suqeim–Al Qudra Corridor, which stretches from Jumeirah Street to Emirates Road.

As one of Dubai’s key east-west traffic corridors, the project is designed to improve integration with major north-south routes across the city.

Key benefit - Once completed, the corridor will serve residential and development areas with a combined population exceeding one million residents.

=

5. Al Qudra Road Development Project

Major sections of the Al Qudra Road project are already operational, with several new bridges opened to traffic earlier this year. Completed works include a 600-metre bridge linking Al Qudra Road with the road connecting Arabian Ranches and Dubai Studio City.

Additional works under construction include:

  • A 700-metre bridge at the intersection of Al Qudra Road and Sheikh Zayed bin Hamdan Al Nahyan Street

  • A 900-metre bridge carrying traffic towards Dubai city centre and Dubai International Airport

  • 3km of new service roads

Key benefits - Upon full completion, the upgraded intersection will increase vehicle capacity, reduce waiting times by 85 per cent and cut delays from 393 seconds to just 60 seconds.

6. Dubai Islands and Bur Dubai Bridge Connection

One of Dubai’s largest ongoing infrastructure projects is the Al Shindagha Corridor Improvement Project, which aims to dramatically improve traffic flow across the emirate. A major milestone was reached with the Al Khaleej Street Tunnel Project surpassing 80 per cent completion.

The wider development includes:

  • A new bridge over Dubai Creek between the Infinity Bridge and Port Rashid area

  • Dedicated cycling and pedestrian tracks

  • Improved access to Dubai Islands

Key benefits

  • Better connectivity between Dubai Islands and Bur Dubai

  • Travel times along the Al Shindagha Corridor reduced from 104 minutes to 16 minutes by 2030.

7. World Trade Centre Roundabout Development Project

The World Trade Centre Roundabout Development Project is one of the most significant traffic improvement schemes currently underway in Dubai.

The project involves:

  • Five bridges spanning 5km

  • The existing roundabout will be replaced with a traffic light-controlled intersection, helping improve traffic flow and reduce congestion during peak hours.

  • Integration with the Al Mustaqbal Street Development Project

Construction has surpassed 60 per cent completion and is progressing ahead of schedule.

In June 2026, RTA opened a new 1km bridge connecting Sheikh Zayed Road to Sheikh Khalifa bin Zayed Street. The two-lane structure accommodates up to 3,000 vehicles per hour and reduces journey times from six minutes to just one minute. Two additional bridges are scheduled to open in October 2026.

Key Benefits

  • Delay times reduced from 12 minutes to 90 seconds

  • Faster access to Al Karama and Deira

  • Improved traffic flow between key routes across central Dubai

RTA opens two bridges as part of Trade Centre Roundabout Development project easing traffic congestion in Dubai