Philippines: 2,000-MW Maton hydropower project, a ₱457-billion grid 'water battery' for Luzon, faces tough pushback

Project eyes huge capacity boosts for Luzon grid, faces scrutiny over community, consent

Last updated:
6 MIN READ
A view of the existing Caliraya-Botocan-Kalayaan (CBK) Pumped Storage Hydropower Plant (PSHPP) — a 789-megawatt facility which straddles the provinces of Laguna Quezon near Manila— the first its kind in Southeast Asia, first energised in 1983. The complex works as a water-powered "mega battery". Maton, proposed in Apayao province, is designed similar to CBK.
A view of the existing Caliraya-Botocan-Kalayaan (CBK) Pumped Storage Hydropower Plant (PSHPP) — a 789-megawatt facility which straddles the provinces of Laguna Quezon near Manila— the first its kind in Southeast Asia, first energised in 1983. The complex works as a water-powered "mega battery". Maton, proposed in Apayao province, is designed similar to CBK.
CBK

Manila: A major hydropower project in the Philippines that could provide reliable electricity for more than 2 million households is facing a major hurdle from nearby residents and indigenous people over concerns including disruption, habitat loss and water quality in the project's vicinity.

Environmentalists have also raised potential disruption to freshwater fish populations in the area.

The Maton Pumped-Storage Hydroelectric Project (Maton PSHPP), a planned 2,000-megawatt facility in Apayao province, is designed to act as a large-scale “water battery” that could help stabilise the Luzon "grid" and enables greater integration of intermittent renewables such as solar and wind.

In this innovative solution is designed to pump water from a lower reservoir to an upper reservoir during low-electricity demand hours, and release the water to drive electric turbines almost instantly during high-demand hours.

The Philippine Department of Energy (DOE) approved converting the project from an initial run-of-river (ROR) to a PSHPP configuration on Dec. 27, 2024.

8.7
Claimed capacity of pumped-storage hydropower plant (PSHPP) approved or underway in the Philippines, as part of the renewable energy drive

This formalised Maton's role as a grid-scale storage asset rather than a conventional hydro plant.

On April 29, 2025, the Philippines' Environmental Management Bureau (EMB) under the Department of Environment and Natural Resources (DENR) conducted "public scoping" for the Maton PSHPP in Upper Maton, Pudtol town, in Apayao province as part of the Environmental Impact Assessment (EIA) process, where a number of concerns by residents, indigenous people and their advocates were raised.

In June 2026, the Board of Investments (BOI) granted “green-lane” status to 11 renewable energy projects totaling ₱509.2 billion, led by Maton’s ₱457-billion valuation.

The move is intended to fast-track permitting and approvals.

If the Maton project proponents do manage to hurdle the environmental challenges, it will be one of just a handful of PSHPP facilities in the country.

The Philippines aims to triple its renewable energy capacity by 2030.

Coal currently accounts for roughly 60% of actual electricity generation in the Asian nation.

The Philippines' long-term energy planning targets an three-fold increase in renewables from the baseline capacity recorded in 2010.

The National Renewable Energy Program (NREP) has set target of 15.3 GW from the 2010 baseline of 5.1GW. More broadly, the nation aims for renewables to make up 35% of the power generation mix at the end of the current decade.

WATER-POWERED 'BATTERY': The only existing PSHPP in the Philippines is the Caliraya-Botocan-Kalayaan (CBK) Hydroelectric Power Plant in the provinces of Laguna and Quezon, just outside Manila. The 789-megawatt facility is the first-of-its-kind powerplant in Southeast Asia, energised in 1983. In February 2026, CBK was officially turned over by the Philippine government to a consortium led by Aboitiz on a 25-year build-repair-operate-maintain-transfer (BROMT) concession under the PPP Law (RA No. 11966) with the Manila government, in a ₱36.27 billion deal. CBK serves as a critical energy buffer for the Luzon grid. Its ability to store energy (in the upper reservoir) enables it to rapidly dispatch power by flowing water from Caliraya Lake to Laguna Bay.

What to know about Maton

  • Capacity and function: The facility is planned at 2,000 MW of installed generating capacity, using an upper and lower reservoir system to pump water uphill during low-demand periods and release it through turbines when power is needed, providing both energy storage and peaking capacity.

  • Location: It will be sited in Barangays Upper Maton and Lt. Balag in Pudtol, with associated works affecting nearby Kabugao, Apayao, along the Maton River system.

  • Developer and contract: Pan Pacific Renewable Power Philippines Corp. (PPRPPC) holds Hydropower Service Contract No. 2022-02-918, awarded by the Department of Energy (DOE) on March 25, 2022.

  • Cost estimates: Baseline capital cost is estimated at ₱261.7 billion, while a higher ₱457 billion figure has been cited in Board of Investments (BOI) “green-lane” tracking for the project among a batch of renewable investments.

Worldwide distribution of pumped storage capacity (GW) at the end of 2016

Latest updates (as of August 2026)

  • Design change approved: DOE approved converting the project from an initial run-of-river hydropower scheme to a pumped-storage configuration on Dec. 27, 2024, formalising its role as a grid-scale storage asset rather than a conventional hydro plant.

  • Environmental review underway: The Environmental Management Bureau (EMB) of the Department of Environment and Natural Resources (DENR) conducted public scoping for the Maton PSHPP on April 29, 2025, in Upper Maton, Pudtol, as part of the Environmental Impact Assessment (EIA) process.

  • Green-lane status: In June 2026, the BOI granted “green-lane” status to 11 renewable energy projects totaling ₱509.2 billion, led by Maton’s ₱457-billion valuation, a move intended to fast-track permitting and approvals.

  • Grid impact studies: As of early 2026, the Maton project had the highest proposed capacity among energy projects undergoing system impact studies with the National Grid Corporation of the Philippines (NGCP), underscoring its potential role in Luzon’s transmission planning.

The Philippines has an estimated 1,800 waterfalls and numerous dams, including 15 run-of-the-river systems. Altogether, these megastructures produce gigawatts (GW) of electricity to power millions of households. With at least 20 hydropower projects in the pipeline, this unprecendented move has potential to generate multiple gigawatts of electricty, according to the Department of Energy. The abundance of rivers and natural water falls makes the Philippines an ideal place to harness hydroelectric power.

Why it matters for the grid

Pumped-storage hydro is one of the few proven technologies capable of storing hundreds to thousands of megawatt-hours and discharging over many hours, making it a key enabler for high shares of variable renewables.

For the Luzon grid, a 2,000-MW facility could provide:

  • Peaking and balancing power during evening demand spikes and when solar output drops.

  • Frequency regulation and reserve services to maintain system stability as more wind and solar come online.

  • Deferred or reduced need for additional fossil-fuel peakers, supporting the country’s decarbonization goals.

Community and consent

Large hydro projects in Apayao have faced scrutiny over Free, Prior and Informed Consent (FPIC) processes with Isnag indigenous communities, particularly for Pan Pacific’s earlier Gened 1 and Gened 2 hydropower projects, where the National Commission on Indigenous Peoples (NCIP) previously deferred decisions amid alleged "irregularities" and local opposition.

While the Maton PSHPP is a separate undertaking, its development in the same province means FPIC compliance and community engagement remain critical to project timelines and social acceptance.

Technical snapshot

  • Installed capacity: 2,000 MWeia.emb.gov+2

  • Estimated cost: ₱261.7 billion (baseline) / ₱457 billion (BOI green-lane tracking)

  • Site: Barangays Upper Maton and Lt. Balag, Pudtol; Kabugao, Apayao

  • Type: Pumped-storage hydroelectric plant using Maton River reservoirs

  • Service contract: HSC No. 2022-02-918, awarded March 25, 2022; design amended to pumped-storage on Dec. 27, 2024

Sign up for the Daily Briefing

Get the latest news and updates straight to your inbox