DEWA raises production capacity of first project of MBR Solar Park’s 5th phase to 330MW
Dubai: The production capacity of the first project of the fifth phase of the Mohammed bin Rashid Al Maktoum Solar Park has increased from 300 megawatts (MW) to 330MW, announced Saeed Mohammed Al Tayer, MD & CEO of Dubai Electricity and Water Authority (DEWA).
This results from using the latest solar photovoltaic bifacial technologies with Single Axis Tracking to increase energy production. The 900MW fifth phase, with investments of Dh2.058 billion, is 60 per cent complete with 4.225 million safe working hours without injuries.
“At DEWA, we work in line with the vision and directives of His Highness Sheikh Mohammed bin Rashid Al Maktoum, Vice President, Prime Minister and Ruler of Dubai, to promote sustainability and innovation and transform into a sustainable green economy, by increasing the share of clean and renewable energy. This achieves the Dubai Clean Energy Strategy 2050 and the Dubai Net Zero Carbon Emissions Strategy to provide 100 percent of Dubai’s total power capacity from clean energy sources by 2050,” Al Tayer said.
“The Mohammed bin Rashid Al Maktoum Solar Park, the largest single-site solar park in the world, is our biggest project to achieve this vision. It has a planned capacity of 5,000MW by 2030. The clean energy share is currently 11.38 per cent of Dubai’s energy mix, and it will reach 13.3 percent in Q1 of 2022.
The current capacity at the Solar Park is 1527MW using solar photovoltaic panels. DEWA is implementing more projects with a total capacity of 1,333MW using solar photovoltaic and Concentrated Solar Power (CSP) in addition to future phases to reach 5,000MW by 2030,” he said.
In November 2019, DEWA announced the consortium led by ACWA Power and Gulf Investment Corporation as the Preferred Bidder to build and operate the 900MW 5th phase of the Mohammed bin Rashid Al Maktoum Solar Park, using photovoltaic solar panels based on the Independent Power Producers (IPPs) model. To implement the project, DEWA established Shuaa Energy 3 in partnership with the consortium led by ACWA Power and Gulf Investment Corporation.
Waleed Bin Salman, Executive Vice President of Business Development and Excellence at DEWA, said that work in the fifth phase of the Solar Park is going on as per the targeted timeline. The second project is now 57 per cent complete.
DEWA owns 60 per cent of the company, and the consortium owns the remaining 40 percent. DEWA achieved a world record by receiving the lowest bid of US$1.6953 cents per kilowatt hour (kW/h) for this phase.